Change order checklist: what to include and how to get it signed

By Obsidian Dynamics · Published November 20, 2026 · 6 min read

A change order is a written agreement, signed by the customer, that adds to or changes the work in an existing contract. A good one describes the extra work, explains why it's needed, shows the price and the effect on the schedule, and is signed before the extra work starts.

The 9-point change order checklist

Whether you use a paper form, a PDF or an app, every change order should cover these points:

  1. Job and customer details. Project name and address, the customer's name and contact information, and your business details.
  2. A reference to the original contract. The contract date or number, so it's clear which agreement this changes.
  3. A change order number. Number them in sequence (CO-001, CO-002…) so nothing gets skipped or confused.
  4. A plain-language description of the change. What will be added, removed or done differently, including materials, finishes and quantities.
  5. The reason for the change. Customer request, hidden condition discovered, code requirement, or design change. This matters if the bill is ever questioned.
  6. Photos. Before-work photos of the area or the condition you found. A photo of a rotted joist settles arguments a paragraph can't.
  7. An itemized price. Labor, materials and other costs as separate lines, and the total added to (or removed from) the contract price.
  8. Schedule impact. How many days the change adds, if any, so the customer doesn't later blame you for a late finish.
  9. Signatures and dates. The customer's signature, ideally from the same person who signed the original contract, plus the date. Keep a copy, and give one to the customer.

Tip: Add a line stating that once signed, the change order becomes part of the original agreement. Many contractors put this in their contract template too.

When should a change order be signed?

Before the extra work starts. Once the work is done, you've lost most of your leverage. If the customer later disputes the price or says they never asked for it, the financial risk is yours.

That's why change orders that wait until "we'll sort it out at the end" cause so many disputes. The best time is the moment the request is made: in the driveway, in the kitchen, or when you open the wall and find the problem.

Why a text message or verbal OK isn't enough

A verbal yes leaves no record. A text thread is better, but it usually doesn't prove what the customer actually saw: which photos, which price, and which version of the scope. Common problems:

  • The price was discussed in one message and the scope in another.
  • The customer replied "ok" to a question that wasn't specific.
  • There's no record of when they agreed or whether anything changed afterward.

A signed change order puts the scope, photos, price and signature in one document, with a date.

Can a customer sign a change order electronically?

In the United States, electronic signatures are generally recognized under the federal ESIGN Act and state laws based on the Uniform Electronic Transactions Act (UETA), as long as the signer agrees to sign electronically. That means a customer can usually approve a change order on their phone.

This isn't legal advice. Some states have specific rules for home improvement contracts and changes to them, and your contract may set its own requirements. Check with your state's contractor licensing board or an attorney.

Common change order mistakes

  • Starting before it's signed. The most expensive mistake on the list.
  • Vague descriptions. "Extra electrical" invites a dispute; "add four recessed LED lights in the kitchen ceiling on a new dimmer" doesn't.
  • A single lump-sum price. Itemized labor and materials are easier for customers to accept and harder to argue with.
  • No photos. Hidden conditions disappear once you fix them. Photograph them first.
  • Editing after it's signed. If something changes, write a new change order instead of altering the signed one.

Doing this on your phone

ChangeProof, our change order app for contractors, is built around this checklist. You photograph the work, price it line by line and text the customer a link. They review and sign in their phone's browser with no app, and you both get a time-stamped PDF. Each change order is locked and fingerprinted when sent, so you can show it wasn't changed afterward.